Preparepm home
  FAQ
  PMP Tutorial
  Mock exam 1
  Mock exam 2
  Renew PMP
  Other sites
  PMP Books
  Edwel
  PMBOK changes
  Software
  About PreparePM
  Our partners
   Tutorial Topics
  Introduction
  Fundamentals
  Integration
  Scope
  Time
  Cost
  Risk
  Quality
  HR
  Communication
  Procurement
  Ethics
   Practice questions
  Mock Exam 1
  Communication
  Cost
  HR
  Introduction
  Quality
  Risk
  Schedule
  Scope
  Procurement
  Integration
   PgMP Certification
  PgMP FAQ
  Closure
  Execution
  Initiation
 
Welcome to www.preparepm.com - Your tool for PMP Certification


home | tutorial | Mock Exam | Books | Questions

Questions on Project Communication Management

  1. The process of Manage Stakeholders Expectations is part of which process group?
    1. Planning
    2. Monitoring and Control
    3. Executing
    4. Initiating

  2. The project you are managing has nine stakeholders. How many channel of communications are there between these stakeholders?
    1. 9
    2. 8
    3. 45
    4. 36

  3. Which of the following is not an example of formal communication?
    1. Contract
    2. email
    3. Project status report
    4. Status meeting

  4. Which of the following process is not included in project communication knowledge area?
    1. Documenting Project Closure
    2. Plam Communications
    3. Distribute Information
    4. Managing Stakeholder Expectations

Answers

  1. c. Manage Stakeholder Expectations is part of executing process group.
  2. d. There will be (9*8)/2 channel of communication.
  3. b. Communication via email is not considered a formal communication.
  4. a. Document Project Closure is not a process in Project communication knowledge area.