perparepm is thankful to Neeraj Kanojia for providing these questions.
Reserve Analysis a technique NOT used in:
Cost Estimate Costs
Determine Budget
Control Costs
Estimate Activity Duration
A Project with a total funding of $100,000 finished with a BAC value of $95,000. What term can BEST describe the difference of $5,000?
Cost Variance
Management Overhead
Management Contingency Reserve
Schedule Variance
Project Cost Management Plan is created as a part of:
Develop Project Management Plan process
Estimate Costs process
Determine Budget process
Control Costs process
A particular project in the domain of civil construction requires that every on-site worker be insured. Which of the following inputs BEST conveys this requirement to the Estimate Costs process so that the insurance cost is estimated and subsequently budgeted:
Enterprise Environmental Factor
Organizational Process Assets
Project Scope Statement
Project Management Plan
_____________ is not a part of the project cost baseline but is included in the project budget:
Activity Cost Contingency Reserve
Management Contingency Reserve
Management Overheads
Project Management Planing
___________ is not part of the Earned Value calculations.
Known Unknowns
Unknown Unknowns
Project Budget
Amount of work completed
What is the BEST way to make an accurate forecasting of ETC?
Manual Forecasting of cost of remaining work.
BAC – EV
(BAC – EV)/CPI
EAC - AC
If the Earned Value is equal to Actual Cost, it means:
Project is on budget and on schedule
Schedule Variance Index is 1
There is no schedule variance
There is no cost variance
Trend Analysis is BEST described as:
Analyzing performance of similar projects over time
Examining project performance over time
Calculating Earned Value
Calculating Cost Variance
Which of the following is not done as part of Performance Measurements?
Calculating Planned Value
Calculating Earned Value
Calculating ETC
Calculating Cost Variance
Management Contingency Reserve is identified in which process:
Estimate Activity Duration
Estimate Costs
Determine Budget
Estimate Activity Resources
Project Cost Management Plan is created as a part of:
Develop Project Management Plan process
Estimate Cost process
Determine Budget process
Control Cost process
A particular project in the domain of civil construction requires that every on-site worker be insured. Which of the following inputs BEST conveys this requirement to the Cost Estimation process so that the insurance cost is estimated and subsequently budgeted?
Enterprise Environmental Factor
Organizational Process Assets
Project Scope Statement
Project Management Plan
Analogous Cost Estimating is
Generally Accurate
Generally less accurate
Uses statistical relationship between historical data and other variables
Bottom-up estimating
Which is NOT true about Analogous Cost Estimating
Uses Expert Judgment
Used when reference projects are similar
Does not require high expertise on part of estimators as estimates are based on previous projects
Useful in early phases of the project
Answers
C
C.
At completion the BAC represents the revised Cost baseline for the project. Management reserves are not part of the cost baselines but they are part of the Project Funding requirements. Therefore the difference between the Cost Baseline and Funding requirement at Project completion is Management Contingency Reserve.
A
C
B
B
A
D.
EV – AC = Cost Variance. Therefore if EV = AC, the Cost Variance is zero (i.e. Project is on budget (but not necessarily on schedule, as there is not enough information on schedule variance)
B
B
C
A.
Note that there is no separate process in the Project Cost Estimation knowledge area to develop a cost management plan.
C.
Project Scope Statement usually contains assumptions and constraints.