perparepm is thankful to Neeraj Kanojia for providing these questions.
Activity Definition is typically performed by which of the following:
Project Manager who created the WBS
Project Team Members responsible for the work package
Project Officer
Project Stakeholder
Which of the following is not an activity attribute:
Person responsible for the activity
Location where to perform the activity
Time when to perform the activity
Leads and Lags
Which of the following does NOT generate changes to the Project documents:
Define Activities
Sequence Activities
Estimate Activity Resources
Estimate Activity Durations
Which of the following may generate a milestone list:
Define Activities
Sequence Activities
Estimate Activity Resources
Estimate Activity Durations
In PDM, which of the following relationships is rarely used:
Finish-to-Start
Start-to-Finish
Start-to-Start
Finish-to-Finish
A schedule activity may begin 10 days before the predecessor activity finishes. This is an example of:
Finish-to-Start
Start-to-Finish
Start-to-Start
Finish-to-Finish
A schedule activity may begin 10 days before the predecessor activity finishes. This is an example of:
ADM
PDM
A dependency with lag
A dependency with lead
The following BEST describes a subnetwork:
Precedence Diagramming Method [PDM]
Arrow Diagramming Method [ADM]
Fragment Network
Activity-On-Node [AON]
A Project Manager in-charge of a Software Development projects is creating a project schedule network diagram for the code development component of the project. This is an example of:
Precedence Diagramming Method [PDM]
Arrow Diagramming Method [ADM]
Fragment Network
Activity-On-Node [AON]
What-if scenario analysis is done as a part of which process:
Sequence Activities
Define Activities
Develop Schedule
Control Schedule
AON refers to:
Precedence Diagramming Method [PDM]
Arrow Diagramming Method [ADM]
Fragment Network
Mandatory Dependencies
AOA refers to:
Precedence Diagramming Method [PDM]
Arrow Diagramming Method [ADM]
Fragment Network
Mandatory Dependencies
Activity Resource Requirements is an input to which of the following processes:
Estimate Activity Durations
Control Schedule
Estimate Activity Resources
Sequence Activities
Dummy relationships or dummy activities can be used in which of the following Activity Sequencing techniques:
Precedence Diagramming Method [PDM]
Arrow Diagramming Method [ADM]
Fragment Network
Schedule Network Templates
Which of the following is NOT an input to the Sequence Activities process:
Project Scope Statement
Activity Attributes
Activity List
Change Requests
Which of the following is a technique for Sequence Activities:
Precedence Diagramming Method [PDM]
Arrow Diagramming Method [ADM]
Rolling Wave Planning
Mandatory Dependencies
Reserve Analysis is a technique for:
Define Schedule
Sequence Activities
Estimate Activity Resources
Estimate Activity Durations
Resource Leveling is a technique for:
Develop Schedule
Sequence Activities
Estimate Activity Resources
Estimate Activity Durations
Following can be BEST described as a kind of dependency that can create arbitrary float values and limit scheduling options:
Mandatory dependency
Discretionary dependency
Start-to-Finish dependency
External dependency
Critical path method is used in which of the following processes:
Sequence Activities
Define Activities
Develop Schedule
Estimate Activity Durations
Parametric Estimating is done as a part of which process:
Sequence Activities
Develop Schedule
Estimate Activity Resources
Estimate Activity Durations
Identification of Mandatory Dependencies is BEST done during which process:
Sequence Activities
Develop Schedule
Define Activities
Estimate Activity Duration
Resource reallocation from non-critical to critical activities is an example of which Project Scheduling technique:
Critical Path Method
Schedule Compression
What-if Analysis
Resource Leveling
Knowledge of best practices in a particular area is MOST likely to give rise to which of the following dependencies:
Finish-to-Start dependency
Soft Logic
Mandatory dependency
External dependency
A Project Manager is preparing a Project Schedule network diagram. During the diagram development, she removes a dependency between two tasks that was defined in an earlier stage. After the network diagram is completed, she updates activity attributes for the two tasks. This is an example of:
Define Activities
Sequence Activities
Develop Schedule
Lack of change control
Reserve Analysis involves:
Estimating by multiplying the quantity of work by productivity rate
Incorporating time buffers into the activity duration estimates
Developing project schedule with contingency reserves as a recognition of the schedule risk
Adding resource reserves to the activity resource estimates
Which of the following is not true for Resource Leveling:
Project schedule is build with resource buffers to prevent schedule slippage
Project’s Critical path may be altered
Resource based scheduling method
Reverse resource allocation scheduling
Answers
Answer: B
PMBOK Pg. 134
Answer: C
Activity attributes are an input for project schedule development; therefore, the scheduling information is not a part of the activity attribute.
Answer: A. Project document updates is an output to all processes in Project Time Management process area except Define Activities.
Answer: A
Answer: B
Answer: A
Answer: D
Note that this dependency can be represented by both ADM and PDM techniques.
Answer: C
Answer: C
It is not clear what Activity Sequencing technique is the Project Manager using; however, it is evident that she is developing a schedule network diagram for only part of the project (not the entire project)
Answer: C
Answer: A
Answer: B
Answer: A
One of the outputs of Estimate activity resources is Activity Resource Requirements.
Sequence Activities establishes logical dependencies between activities. Activity Resource requirements do not play an important role in determining the sequence.
Answer: B
Answer: D
Approved Change Requests is not a valid input to Sequence Activities process.
Answer: A
Answer: D
Answer: A
Answer: B
Answer: C
Answer: D
Answer: A
Answer: D
Answer: B
Discretionary dependencies often result from best practices. This kind of dependency is also known as Soft Logic, Preferential Logic, or Preferred Logic.
Answer: D
The Project manager is preparing the project schedule network diagram which implies she is in the Activity scheduling process. This process can generate changes to the Activity definition and Activity Attributes; however, such changes should go thru the Integrated Change Control and only upon approval should they be made.
Answer: B
Answer C might seem more likely, but note the fine difference that Reserve Analysis is purely a technique of determining activity duration, not a schedule development technique.
Answer: A
Resource leveling involves creating a resource constrained project schedule.