Home
Project Time Management

An Introduction To Our Online PMP Training Course

PMP Training - What you receive


Here is what you receive with our full PMP exam prep class:
  • Print copy of our 396-page course manual shipped directly to your home
  • Print copy of the 756-page PMBOKĀ® Guide 6th Edition shipped to your home
  • 100 days access to our fast, reliable Learning Platform
  • 10 hours of instructor-led online instruction
  • 1 full day of in-person classroom training at one of our 20 training facilities
  • Over 1200 sample questions with simulator
  • Tracking analytics to follow your progress
  • Certificate documenting 35 contact hours of PM education
  • Near perfect 99% pass rate

  • Title: PMP Certification Training
  • Format: Blend of Online and Traditional Classroom Instruction
  • PMI Approved Hours: 35 Contact Hours
  • Tuition: $595

LOOKING TO UPGRADE INTO LIVE CLASSROOM TRAINING? Join a 1-day in-person class taught by a veteran PreparePM instructor. Choose from over 20 locations.

Project Schedule Management

PREV: Scope       UP NEXT: Cost Management


The knowledge area of Project Time Management consists of the following processes -

Time Management Processes

Process Project Phase Key Deliverables
Plan Schedule Management Planning
Define Activities Planning Activity List, Milestone list
Sequence Activities Planning Project Schedule network diagrams
Estimate Activity Resources Planning Activity resource requirements,
Resource breakdown structure
Estimate Activity Durations Planning Activity duration estimates
Develop Schedule Planning Project Schedule
Control Schedule Monitoring and Controlling Work Performance measurements,
Change Requests


  • The Define Activities process has the following Inputs, Tools and Techniques and Outputs -

    Define Activities Process

    Inputs Tools and Techniques Outputs
    Scope baseline Decomposition Activity list
    Enterprise environmental factors Rolling wave planning Activity attributes
    Organizational process assets Templates Milestone list
    Expert judgment


  • The Sequence Activities process has the following Inputs, Tools and Techniques and Outputs -

    Sequence Activities Process

    Inputs Tools and Techniques Outputs
    Project scope statement Precedence diagram method (PDM) or AON Project schedule network diagrams
    Activity List Applying leads and lags Project document updates
    Activity attributes Schedule Network Templates
    Milestone list Dependency determination
    Organizational process assets


  • The Estimate Activity Resources process has the following Inputs, Tools and Techniques and Outputs -

    Estimate Activity Resources Process

    Inputs Tools and Techniques Outputs
    Activity List Expert judgment Activity resource requirements
    Activity attributes Alternative analysis Resource breakdown structure
    Resource calendars Published estimating data Project document updates
    Enterprise environmental factors Bottom-up estimating
    Organizational process assets Project Management software


  • The Estimate Activity Durations process has the following Inputs, Tools and Techniques and Outputs -

    Estimate Activity Durations Process

    Inputs Tools and Techniques Outputs
    Activity list Expert judgment Activity duration estimates
    Activity attributes Analogous estimating Project document updates
    Activity resource requirements Parametric estimating
    Resource calendars Three-point estimates
    Project scope statement Reserve analysis
    Enterprise environmental factors
    Organizational process assets


  • The Develop Schedule process has the following Inputs, Tools and Techniques, and Outputs-

    Develop Schedule Process

    Inputs Tools and Techniques Outputs
    Organizational process assets Schedule network analysis Project Schedule
    Project scope statement Critical path method Schedule baseline
    Activity List Schedule Compression Schedule data
    Activity attributes What-if scenario analysis Project document updates
    Project Schedule Network diagram Resource levelling
    Activity Resource requirements Critical chain method
    Resource Calendars Scheduling tool
    Activity duration estimates Applying calendars
    Project Management Plan -
    Risk Register
    Adjusting Leads and Lags
    Enterprise environmental factors


  • The Control Schedule process has the following Inputs, Tools and Techniques and Outputs -

    Control Schedule Process

    Inputs Tools and Techniques Outputs
    Project management plan Performance reviews Work performance measurements
    Project schedule Variance analysis Organizational process assets updates
    Work performance information Project management software Change requests
    Organizational process assets Resource leveling Project management plan updates
    What-if scenario analysis Project document updates
    Adjusting leads and lags
    Schedule compression
    Scheduling tool


  • Bar charts (or Gantt charts) are used to display tasks and their dates in a graphical fashion. They are used to display information of the type task 1 is scheduled from date A to date B. Typically the date range is displayed in the X-axis and the tasks on the Y-axis. Bar charts do not show task dependencies. They are generally used to track progress and show to the team.
  • Milestone charts are similar to bar charts but display only major events. They display major milestones (for example bridge design completed). They are used to report status to Management.
  • Network diagrams are used to display activities and their dependencies. Network diagrams can be used to perform critical path analysis. Network diagrams can also be used to perform crashing and fast tracking of the project.
    There are two type of network diagrams -
    • Activities on Node (or Precedence)
    • Activities on Arrow (or AOA)
    Precedence is most commonly used. AON and AOA cannot have loops or conditional relationships.
  • An activity in a network diagram is displayed as shown below.
    Activity name
    Activity Number Estimate

    As an example -

    Documentation
    2 5 days
    In the above example Documentation is activity number 2 and is estimated to last 5 days.

  • Precedence (or Activity on Node) diagrams can be used to display four type of relationship between activities. These are
    • Finish-To-Start
    • Start-To-Start
    • Start-To-Finish
    • Finish-To-Finish

    Finish-to-start relationship means the dependent activity cannot start until the first activity is finished. This is the most common way to represent relationships between activities.

  • Activity on Array (AOA) network diagrams have the following characteristics.
    • AOA only uses Finish-To-Start relationship between tasks.
    • PERT and CPM can only be used with AOA.
    • Dummy events are shown with dotted lines. They do not take any time. They show dependencies between tasks.
  • Longest path through the network diagram is called the critical path. The activities on the critical paths are called critical activities.
  • Lags are inserted waiting times in between tasks. For example Task B cannot start until three days after task A completes.
  • Slack or Float is the amount of time a task can be delayed without delaying the project. Tasks on the critical path have zero float.
  • Critical Path Method (CPM) has the following characteristics.
    • It uses one time estimate per activity
    • It can be drawn only using AOA diagrams
    • It can have dummy events
  • Program Evaluation and Review Technique (PERT) has the following characteristics.
    • It uses three estimates per activity - optimistic, pessimistic and most likely
    • It can be drawn only using AOA diagrams
    • It can have dummy events
  • PERT utilizes more information than CPM as it considers the "Pessimistic" and "Optimistic" values in addition to the "Most Likely" value in its calculations. The following are formulae used by PERT -
     Mean = (P + 4M + O)/6
     Standard Deviation = (P-O)/6
     Variance = ((P-O)/6)2

    Here P is the pessimistic estimate, O is the optimistic estimate and M is the most likely estimate.
  • GERT is another type of network diagram. It can support looping.
  • If a project has more than one critical paths then the risk to the project increases.
  • Resource levelling refers to keeping the resources same across the duration of the project.
  • Questions on Project Schedule Management are available in Schedule Questions.

    UP NEXT: Cost Management

    Upcoming Classes

    Apr 1
    Atlanta - 1 Day Boot Camp

    859 Mount Vernon Parkway
    Preparepm Training Center
    Atlanta, GA 30328
    8:00 AM-6:00 PM

    Purchase

    Apr 1
    Orlando - 1 Day Boot Camp

    8325 South Park Circle
    PreparePM Training Center
    Orlando, FL. 32819
    8:00 AM-6:00 PM

    Purchase

    Apr 1
    San Francisco - 1 Day Boot Camp

    One Front Street
    PreparePM Training Center
    San Francisco, CA. 94111
    8:00 AM-6:00 PM

    Purchase

    Apr 3
    Minneapolis - 1 Day Boot Camp

    435 Ford Road
    PreparePM Training Center
    Minneapolis, MN. 55426
    8:00 AM-6:00 PM

    Purchase

    Apr 7
    Dallas - 1 Day Boot Camp

    12400 Coit Road
    PreparePM Training Center
    Dallas, TX 75251
    8:00 AM-6:00 PM

    Purchase

    Apr 7
    Houston - 1 Day Boot Camp

    11451 Katy Freeway
    PreparePM Training Center
    Houston, TX 77079
    8:00 AM-6:00 PM

    Purchase

    Apr 7
    New York - 1 Day Boot Camp

    63 West 35th Street
    PreparePM Training Center
    New York, NY. 10001
    8:00 AM-6:00 PM

    Purchase

    Apr 8
    Boston - 1 Day Boot Camp

    61 Exeter St
    PreparePM Training Center
    Boston, MA 02116
    8:00 AM-6:00 PM

    Purchase

    Apr 13
    Austin - 1 Day Boot Camp

    10801 North Mopac Expressway
    PreparePM Training Center
    Austin, TX 78759
    8:00 AM-6:00 PM

    Purchase

    Apr 13
    Chicago - 1 Day Boot Camp

    203 North LaSalle
    PreparePM Training Center
    Chicago, IL. 60601
    8:00 AM-6:00 PM

    Purchase

    Apr 13
    Chicago - 1 Day Boot Camp

    203 North LaSalle
    PreparePM Training Center
    Chicago, IL. 60601
    8:00 AM-6:00 PM

    Purchase

    Apr 13
    Los Angeles - 1 Day Boot Camp

    915 Wilshire Blvd
    PreparePM Training Center
    Los Angeles, CA 90017
    8:00 AM-6:00 PM

    Purchase

    Apr 14
    Denver - 1 Day Boot Camp

    10004 Park Meadows
    PreparePM Training Center
    Centennial, CO. 80124
    8:00 AM-6:00 PM

    Purchase

    Apr 15
    Dallas - 1 Day Boot Camp

    12400 Coit Road
    PreparePM Training Center
    Dallas, TX 75251
    8:00 AM-6:00 PM

    Purchase

    Apr 15
    Phoenix - 1 Day Boot Camp

    4615 East Elwood Street
    PreparePM Trainin Center
    Phoenix, AZ. 85040
    8:00 AM-6:00 PM

    Purchase

    For more dates and locations, please visit our individual city pages, or call our office to speak with a PreparePM representative.

    Testimonials

    • I took the boot camp last Monday thru Thursday and I passed my PMP, on my first attempt, on Friday afternoon.

      Lorna Lavelle, PMP
    • I took my bootcamp last week and passed the next day. My instructor was easily one of the best instructors I've ever had.

      Timothy Hopkins, PMP
    • I leveraged the course as somewhat of a capstone to my preparation period. I took the exam the very next day after the boot camp ended, and passed.

      Acie Slade PMP