Home
Questions on Project Time Management

An Introduction To Our Online PMP Training Course

PMP Training - What you receive


Here is what you receive with our full PMP exam prep class:
  • Print copy of our 396-page course manual shipped directly to your home
  • Print copy of the 756-page PMBOK® Guide 6th Edition shipped to your home
  • 100 days access to our fast, reliable Learning Platform
  • 10 hours of instructor-led online instruction
  • 1 full day of in-person classroom training at one of our 20 training facilities
  • Over 1200 sample questions with simulator
  • Tracking analytics to follow your progress
  • Certificate documenting 35 contact hours of PM education
  • Near perfect 99% pass rate

  • Title: PMP Certification Training
  • Format: Blend of Online and Traditional Classroom Instruction
  • PMI Approved Hours: 35 Contact Hours
  • Tuition: $595

LOOKING TO UPGRADE INTO LIVE CLASSROOM TRAINING? Join a 1-day in-person class taught by a veteran PreparePM instructor. Choose from over 20 locations.

Questions on Project Time Management

PREVIOUS: Scope       UP NEXT: Risk

Questions

  1. Activity Definition is typically performed by which of the following:
    1. Project Manager who created the WBS
    2. Project Team Members responsible for the work package
    3. Project Officer
    4. Project Stakeholder
    CORRECT: Answer: B
  2. Which of the following is not an activity attribute:
    1. Person responsible for the activity
    2. Location where to perform the activity
    3. Time when to perform the activity
    4. Leads and Lags
    CORRECT: Answer: C Activity attributes are an input for project schedule development; therefore, the scheduling information is not a part of the activity attribute.
  3. Which of the following does NOT generate changes to the Project documents:
    1. Define Activities
    2. Sequence Activities
    3. Estimate Activity Resources
    4. Estimate Activity Durations
    CORRECT: Answer: A. Project document updates is an output to all processes in Project Time Management process area except Define Activities.
  4. Which of the following may generate a milestone list:
    1. Define Activities
    2. Sequence Activities
    3. Estimate Activity Resources
    4. Estimate Activity Durations
    CORRECT: Answer: A
  5. In PDM, which of the following relationships is rarely used:
    1. Finish-to-Start
    2. Start-to-Finish
    3. Start-to-Start
    4. Finish-to-Finish
    CORRECT: Answer: B
  6. A schedule activity may begin 10 days before the predecessor activity finishes. This is an example of:
    1. Finish-to-Start
    2. Start-to-Finish
    3. Start-to-Start
    4. Finish-to-Finish
    CORRECT: Answer: A
  7. A schedule activity may begin 10 days before the predecessor activity finishes. This is an example of:
    1. ADM
    2. PDM
    3. A dependency with lag
    4. A dependency with lead
    CORRECT: Answer: D Note that this dependency can be represented by both ADM and PDM techniques.
  8. The following BEST describes a subnetwork:
    1. Precedence Diagramming Method [PDM]
    2. Arrow Diagramming Method [ADM]
    3. Fragment Network
    4. Activity-On-Node [AON]
    CORRECT: Answer: C
  9. A Project Manager in-charge of a Software Development projects is creating a project schedule network diagram for the code development component of the project. This is an example of:
    1. Precedence Diagramming Method [PDM]
    2. Arrow Diagramming Method [ADM]
    3. Fragment Network
    4. Activity-On-Node [AON]
    CORRECT: Answer: C It is not clear what Activity Sequencing technique is the Project Manager using; however, it is evident that she is developing a schedule network diagram for only part of the project (not the entire project)
  10. What-if scenario analysis is done as a part of which process:
    1. Sequence Activities
    2. Define Activities
    3. Develop Schedule
    4. Control Schedule
    CORRECT: Answer: C
  11. AON refers to:
    1. Precedence Diagramming Method [PDM]
    2. Arrow Diagramming Method [ADM]
    3. Fragment Network
    4. Mandatory Dependencies
    CORRECT: Answer: A
  12. AOA refers to:
    1. Precedence Diagramming Method [PDM]
    2. Arrow Diagramming Method [ADM]
    3. Fragment Network
    4. Mandatory Dependencies
    CORRECT: Answer: B
  13. Activity Resource Requirements is an input to which of the following processes:
    1. Estimate Activity Durations
    2. Control Schedule
    3. Estimate Activity Resources
    4. Sequence Activities
    CORRECT: Answer: A One of the outputs of Estimate activity resources is Activity Resource Requirements. Sequence Activities establishes logical dependencies between activities. Activity Resource requirements do not play an important role in determining the seq
  14. Dummy relationships or dummy activities can be used in which of the following Activity Sequencing techniques:
    1. Precedence Diagramming Method [PDM]
    2. Arrow Diagramming Method [ADM]
    3. Fragment Network
    4. Schedule Network Templates
    CORRECT: Answer: B
  15. Which of the following is NOT an input to the Sequence Activities process:
    1. Project Scope Statement
    2. Activity Attributes
    3. Activity List
    4. Change Requests
    CORRECT: Answer: D Approved Change Requests is not a valid input to Sequence Activities process.
  16. Which of the following is a technique for Sequence Activities:
    1. Precedence Diagramming Method [PDM]
    2. Arrow Diagramming Method [ADM]
    3. Rolling Wave Planning
    4. Mandatory Dependencies
    CORRECT: Answer: A
  17. Reserve Analysis is a technique for:
    1. Define Schedule
    2. Sequence Activities
    3. Estimate Activity Resources
    4. Estimate Activity Durations
    CORRECT: Answer: D
  18. Resource Leveling is a technique for:
    1. Develop Schedule
    2. Sequence Activities
    3. Estimate Activity Resources
    4. Estimate Activity Durations
    CORRECT: Answer: A
  19. Following can be BEST described as a kind of dependency that can create arbitrary float values and limit scheduling options:
    1. Mandatory dependency
    2. Discretionary dependency
    3. Start-to-Finish dependency
    4. External dependency
    CORRECT: Answer: B
  20. Critical path method is used in which of the following processes:
    1. Sequence Activities
    2. Define Activities
    3. Develop Schedule
    4. Estimate Activity Durations
    CORRECT: Answer: C
  21. Parametric Estimating is done as a part of which process:
    1. Sequence Activities
    2. Develop Schedule
    3. Estimate Activity Resources
    4. Estimate Activity Durations
    CORRECT: Answer: D
  22. Identification of Mandatory Dependencies is BEST done during which process:
    1. Sequence Activities
    2. Develop Schedule
    3. Define Activities
    4. Estimate Activity Duration
    CORRECT: Answer: A
  23. Resource reallocation from non-critical to critical activities is an example of which Project Scheduling technique:
    1. Critical Path Method
    2. Schedule Compression
    3. What-if Analysis
    4. Resource Leveling
    CORRECT: Answer: D
  24. Knowledge of best practices in a particular area is MOST likely to give rise to which of the following dependencies:
    1. Finish-to-Start dependency
    2. Soft Logic
    3. Mandatory dependency
    4. External dependency
    CORRECT: Answer: B Discretionary dependencies often result from best practices. This kind of dependency is also known as Soft Logic, Preferential Logic, or Preferred Logic.
  25. A Project Manager is preparing a Project Schedule network diagram. During the diagram development, she removes a dependency between two tasks that was defined in an earlier stage. After the network diagram is completed, she updates activity attributes for the two tasks. This is an example of:
    1. Define Activities
    2. Sequence Activities
    3. Develop Schedule
    4. Lack of change control
    CORRECT: Answer: D The Project manager is preparing the project schedule network diagram which implies she is in the Activity scheduling process. This process can generate changes to the Activity definition and Activity Attributes; however, such changes should
  26. Reserve Analysis involves:
    1. Estimating by multiplying the quantity of work by productivity rate
    2. Incorporating time buffers into the activity duration estimates
    3. Developing project schedule with contingency reserves as a recognition of the schedule risk
    4. Adding resource reserves to the activity resource estimates
    CORRECT: Answer: B Answer C might seem more likely, but note the fine difference that Reserve Analysis is purely a technique of determining activity duration, not a schedule development technique.
  27. Which of the following is not true for Resource Leveling:
    1. Project schedule is build with resource buffers to prevent schedule slippage
    2. Project’s Critical path may be altered
    3. Resource based scheduling method
    4. Reverse resource allocation scheduling
    CORRECT: Answer: A Resource leveling involves creating a resource constrained project schedule.
You have answered  of 27 questions correctly.

More Options

Visit the Time tutorial to brush up the topic.

UP NEXT: Risk

Upcoming Classes

Mar 2
Atlanta +1 Boot Camp Upgrade

859 Mount Vernon Parkway
Preparepm Training Center
Atlanta, GA 30328
8:00 AM-6:00 PM

Purchase

Mar 3
Baltimore +1 Boot Camp Upgrade

8830 Stanford Blvd.
PreparePM Training Center
Columbia, MD. 21045
8:00 AM-6:00 PM

Purchase

Mar 3
New York +1 Boot Camp Upgrade

63 West 35th Street
PreparePM Training Center
New York, NY. 10001
8:00 AM-6:00 PM

Purchase

Mar 4
Minneapolis +1 Boot Camp Upgrade

435 Ford Road
PreparePM Training Center
Minneapolis, MN. 55426
8:00 AM-6:00 PM

Purchase

Mar 4
Washington DC +1 Boot Camp Upgrade

2121 15th Street
PreparePM Training Center
Arlington VA. 22201
8:00 AM-6:00 PM

Purchase

Mar 5
Boston +1 Boot Camp Upgrade

61 Exeter St
PreparePM Training Center
Boston, MA 02116
8:00 AM-6:00 PM

Purchase

Mar 10
Austin +1 Boot Camp Upgrade

10801 North Mopac Expressway
PreparePM Training Center
Austin, TX 78759
8:00 AM-6:00 PM

Purchase

Mar 11
Chicago +1 Boot Camp Upgrade

203 North LaSalle
PreparePM Training Center
Chicago, IL. 60601
8:00 AM-6:00 PM

Purchase

Mar 16
Detroit +1 Boot Camp Upgrade

26261 Evergreen Road
PreparePM Training Center
Southfield, MI. 48076
8:00 AM-6:00 PM

Purchase

Mar 17
Dallas +1 Boot Camp Upgrade

12400 Coit Road
PreparePM Training Center
Dallas, TX 75251
8:00 AM-6:00 PM

Purchase

Mar 19
Denver +1 Boot Camp Upgrade

10004 Park Meadows
PreparePM Training Center
Centennial, CO. 80124
8:00 AM-6:00 PM

Purchase

Mar 20
Los Angeles +1 Boot Camp Upgrade

915 Wilshire Blvd
PreparePM Training Center
Los Angeles, CA 90017
8:00 AM-6:00 PM

Purchase

Mar 20
Raleigh +1 Boot Camp Upgrade

4 Copley Parkway
PreparePM Training Center Morrisville, NC 27560
8:00 AM-6:00 PM

Purchase

Mar 23
Phoenix +1 Boot Camp Upgrade

4615 East Elwood Street
PreparePM Trainin Center
Phoenix, AZ. 85040
8:00 AM-6:00 PM

Purchase

Mar 24
Houston +1 Boot Camp Upgrade

11451 Katy Freeway
PreparePM Training Center
Houston, TX 77079
8:00 AM-6:00 PM

Purchase

For more dates and locations, please visit our individual city pages, or call our office to speak with a PreparePM representative.

Testimonials

  • I took the boot camp last Monday thru Thursday and I passed my PMP, on my first attempt, on Friday afternoon.

    Lorna Lavelle, PMP
  • I took my bootcamp last week and passed the next day. My instructor was easily one of the best instructors I've ever had.

    Timothy Hopkins, PMP
  • I leveraged the course as somewhat of a capstone to my preparation period. I took the exam the very next day after the boot camp ended, and passed.

    Acie Slade PMP